24.0 FORCE MAJEURE
24.1 No party shall be liable for a failure or delay in performing any of its obligations under this AGREEMENT if, but only to the extent that, such failure or delay is due to causes beyond the reasonable control of the affected party, including: (1) acts of God; (2) fire or explosion (except to the extent caused by the negligence or willful misconduct of the affected party); (3) unusually severe weather; (4) war, invasion, riot or other civil unrest; (5) governmental laws, orders, restrictions, actions, embargoes, or blockages; (6) national or regional emergency; and (7) injunctions, strikes, lockouts, labor trouble, or other industrial disturbances; provided that the party affected shall promptly notify the other of the force majeure condition and shall exert reasonable efforts to eliminate, cure, or overcome any such causes and to resume performance of its obligations as soon as practicable.
|