1、肯定是可以满足的,在设置ECO或直接定义BOM的时候,对组件都有版本和effective date的控制
在bom, eco, component那里都看过了, 这个是默认继承 revised date 的version.
user guide 的描述
'The Revision field displays the current revision of the component as of the revision date of the parent item.'
metalink也有说, 不能选择, 总是最后lastest revision
·
fact: Oracle Bills of Material 11.5.3
·
·
fact: BOMFDBOM - Define Bill of Material
·
·
symptom: Revision Of A Component Item On The Bom Always Defaults To Latest
·
Revision
·
·
change: NOTE ROLE: Would perfer the ability to select from active revisions
·
rather than be forced to choose the latest one.
·
·
cause: This is current functionality.
·
·
fix:
Enhancement request 3051893 has been logged for this issue
所以, 现在看来,唯一能作修改的就是。修改parent item, FG
FG Revision 1, from 08-feb-2006 -> 10-mar-2006
component, revision A,
FG revision 2, after 10-mar-2006
componet, revision B.
可是这样, 运行mrp的时候作测试的时候, mrp就只考虑运行mrp时候FG的revision
我有planned order , as demand for FG, 在10-mar-2006前后, 但是,出来的component需求都是revision A的
是我那里运行错了吗
2. 我觉得也是可是的,但是在mrp workbench 上看不到component revision,只有在release 到pr的时候, 才能看到
3. 基本搞定
4. BPA effective date 是控制整个bpa的
对于一个supplier我们只有一个bpa
这样, 对于componet, revision A,B都是从一个supplier 买,只是价格不同
所以, line 1: Revision A
line 2: Revision B.
我在指定avl的时候, 必须说, component 对应bpa中哪一行, 1 or 2. 这个时候, 就出现矛盾了。 :-(
另外,问一下,大哥作什么的, 怎么感觉那个模块都知道,而且,狂精通 :-)
|