I have the following Problem,
When converting Planned Orders to Production Orders in MD04 and calling C040 this does not take account of my BOM status which is set to
block, but if I create a Production Order directly in CO01 the BOM status is referenced and the creation of the Production order is denied
but this does not happen with MD04 calling CO01.
I have searched OSS and found Note 453755 which is the exact problem I am having, but the note only refers to version 4.6c however we are on
4.7.
Anyone have similar problems please let me know how you resolved it.
Thanks
回复

使用道具 举报

千问 | 2007-9-26 18:42:10 | 显示全部楼层
好像md04展開的工單帶的只是默認的bom吧,如果有需要在工單畫面自行調整..不太清楚是否可以直接在md04中選擇,感覺好像不行,因為run mrp的時候,bom的版本就已經定好了啊!學習
回复

使用道具 举报

千问 | 2007-9-26 18:42:10 | 显示全部楼层
我试了一下,应该是可以更改组件,但不能直接更改版本
有高手来说说
回复

使用道具 举报

千问 | 2007-9-26 18:42:10 | 显示全部楼层
是不是工单中设置的呢?